The project will make central sewer available to approximately 2,650 homes. The project is integrated with a sidewalk project.
Wastewater flow from Area K will be pumped to the Bee Ridge Water Reclamation Facility with a transfer pump station located just south of the Atlantic Water Reclamation Facility.
Construction of Area K east of McIntosh Road began in May 2007 and is expected to be complete in January 2009. Construction of the area west of McIntosh Road began in October 2007 and is expected to be complete in June 2009.
This major construction project will be disrupting to the neighborhood but every effort will be made to minimize the negative impacts. Everyone's cooperation is appreciated. |
|
| Description |
|
| This project includes design and construction of a central sewer system for approximately 2,650 property owners in the Phillippi Creek Septic System Replacement Program - Area K. The central sewer system will replace the need for existing septic systems in this area. The new system will require the installation of sewer piping along rights-of-way and construction of a collection/pumping station that will collect and transfer wastewater to Sarasota County’s Bee Ridge Water Reclamation Facility. |
|
Service Area
|
| Located near the intersection of Webber Street and McIntosh Road |
| Size of Area: |
Approx. 320 acres |
| Approx. Connections: |
2650 |
| Type of System: |
Vacuum Sewer |
|
| | Construction |
|
|
|
| Other Projects |
|
| The construction of a sidewalk and bike path along Webber Street between McIntosh Road and Linwood Street will be included with the construction of the sewer program. | |
|
|
|
Area K |
|

| |
|
|
 |
Contractor installs equipment in vacuum pit for homeowner connections.
| |
|